In case you are concerned with test preparing next you should not get worried even as are usually proudly introducing our own impressive up to date totally free human brain places in addition to up to date simulations in order to effortlessly get ready and also complete analyze together with excellent test may be approved together with large report together with Human brain Eliminate genuine C_TSCM42_65 sample questions VCE. In the event you plan the particular test making use of our own CT tests powerplant, we all ensure the accomplishment inside the initial test.

QUESTION 1
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling. Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?

A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the “simulation mode” option
C. Total planning online
D. Multi-level single-item planning with the “display material list” option

Answer: B

QUESTION 2
What does SAP ERP mean?

A. SAP ERP is a planning system in which extended planning processes can be mapped.
B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution, materials management, production and so on.
C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can be imported.
D. SAP ERP is an application that an enterprise can use to manage its business processes efficiently.

Answer: D

QUESTION 3
Which functions can be triggered before releasing a production order? (Choose three)

A. Confirmation
B. Selection of a routing
C. Scheduling
D. Stock determination
E. Selection of a BOM

Answer: BCE

QUESTION 4
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)

A. Availability check
B. Digital signature
C. Resource selection
D. Electronic batch record
E. Approved master recipes

Answer: BDE

QUESTION 5
Which of the following statements about consumption are correct? (Choose two)

A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
C. Consumption is restructured with the planning run.
D. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.

Answer: BD

QUESTION 6
Where can you define the valid receivers for production order costs?

A. In the valuation variant
B. In the production scheduling profile
C. In the settlement profile
D. In the costing variant

Answer: C

http://www.passleader.com/c-tscm42-65.html

The web test examine components and also test up to date research laboratory training were created in a fashion that once you show up regarding cert it can help to improve upwards the self-assurance stage regarding seeking test. The particular totally free powerplant bunch regarding offers you directly experience of the true C_TSCM42_65 exam. Certain! No matter which amount of the particular Qualification you might be with, be confident you’ll get by means of the test straight away. Oahu is the examination of the right blend and also it helps an individual complete test with initially! Exactly why pick PASSLEADER components when you obtain our own merchandise, we all offer totally free up-date with time regarding a hundred and eighty nights.